QUESTION
Why did this project's predevelopment process take so long?
0:33:57
·
53 sec
Aleena Farishta states that the predevelopment process's length is due to comprehensive tasks like site surveying, diligence, and preparing a site plan, alongside pandemic-related delays.
- The predevelopment process is inherently lengthy, involving detailed site surveying and deep diligence.
- Coordination with sister agencies, such as city planning, is necessary to ensure a technically complete application, especially for land use actions like rezoning.
- The COVID-19 pandemic further delayed the process, though the team is now ready to present the project and hope to move forward.
Kamillah Hanks
0:33:57
Is there a reason why this plan took so long?
Aleena Farishta
0:34:03
For for this project specifically?
0:34:05
Yes.
0:34:06
HPD.
0:34:06
How long?
0:34:08
Thank you.
0:34:09
Yeah.
0:34:09
So the the predevelopment process, you know, It's a it's a very lengthy process.
0:34:15
We know we wish it could be a lot quicker.
0:34:18
During this time, you know, we do a lot of, like, site surveying, deep diligence.
0:34:23
We work on putting together a site plan.
0:34:26
We work with sister agencies such as city planning to make sure we're a technically complete application since we are seeking various land use actions, including a rezoning.
0:34:37
And there was also the pandemic during that time, which slowed down our process a little bit, but we're here before you now.
0:34:44
I'm excited to present this project and hopefully move forward.