Why are there no changes in the capital commitment plan for 2024-2028 despite Borough-based jail project delays and cost increases?

2:38:36

·

65 sec

Video Player is loading.
Current Time 0:00
Duration 0:00
Loaded: 0%
Stream Type LIVE
Remaining Time 0:00
Â
1x
    • Chapters
    • descriptions off, selected
    • captions off, selected

      Assistant Commissioner Alex Maldonado explains that the Department of Design and Construction oversees the budget and schedule for Borough-based jail projects, hence their details are not reflected in the capital commitment plan.

      • The Department of Design and Construction controls the budget and schedule for the Borough-based jail projects.
      • The capital commitment plan does not reflect the budget and timeline changes for these projects.
      • Council Member Adrienne E. Adams inquires about the lack of visible changes in the plan despite known project delays and cost increases.
      • Delays and cost hikes in the Borough-based jail projects are attributed to increased labor and steel prices.