QUESTION
Why are there no changes in the capital commitment plan for 2024-2028 despite Borough-based jail project delays and cost increases?
2:38:36
·
65 sec
Video Player is loading.
Assistant Commissioner Alex Maldonado explains that the Department of Design and Construction oversees the budget and schedule for Borough-based jail projects, hence their details are not reflected in the capital commitment plan.
- The Department of Design and Construction controls the budget and schedule for the Borough-based jail projects.
- The capital commitment plan does not reflect the budget and timeline changes for these projects.
- Council Member Adrienne E. Adams inquires about the lack of visible changes in the plan despite known project delays and cost increases.
- Delays and cost hikes in the Borough-based jail projects are attributed to increased labor and steel prices.