QUESTION
What are the details of the Eastern Parkway and Brownsville library renovation projects, including their budgets, scopes, and projected timelines?
1:05:55
·
74 sec
The Eastern Parkway library renovation is a $20 million full restoration project planned to begin in spring of the following year, with an additional $750,000 requested for initial outfitting.
- The hope is for this project to stay on course despite potential challenges.
- For the Brownsville branch, there is $23.3 million allocated in the fiscal 2024-2028 commitment plan.
- The Brownsville renovation includes a comprehensive overhaul with a rooftop addition.
- Other elements are additional public space, new landscaping, a green roof, security/fire safety upgrades, and sustainability measures to make the branch fossil fuel-free.
Carlina Rivera
1:05:55
In into Brooklyn, can can you provide a status date on the Eastern Parkway in Brownsville overhaul projects and the projected completion date and has DDC remained on target?
Linda Johnson
1:06:06
So Eastern Parkway.
1:06:09
Sorry.
1:06:10
Eastern Parkway is a $20,000,000 full restoration project, which is planned, but not until spring of next year.
1:06:18
We've asked for an additional $750,000 for initial outfitting.
1:06:24
But hopefully, this project will be able to stay on course should things turn around.
1:06:31
I'm sorry.
1:06:31
The other one you asked about was Brownsville.
1:06:34
Tom, not Yes.
1:06:37
Brownsville.
1:06:39
And in Brownsville, the branch has $23,300,000 in the fiscal 20 24-2028 commitment plan for another full branch renovation, which includes a rooftop addition.
1:06:54
This this Project has been in the works for a long time.
1:06:57
Additional public service space, new landscaping, a green roof, security, and fire safety systems, a new system to make it fossil fuel free and sustainable.
← Previous Chapter
What is the status of the Tompkins Square and West New Brighton library renovation projects? What are the projected completion dates and has the Department of Design and Construction remained on schedule?
Next Chapter →
What is the current status and details of the planned expansion of the Corona library branch?