Council Member Carmen De La Rosa inquires about the timeline for submitting the Public Service Corps program report, which was delayed. DCAS representative Katrina Porter confirms that the report will be submitted by the end of November.
- The report was initially due on August 30th, 2024
- DCAS had previously notified the council of a delay
- The report is now expected to be submitted by the end of November
Carmen De La Rosa
0:26:07
Thank you so much for your testimony.
0:26:10
I'll start with a few questions, CCaaS.
0:26:14
So in 2023, the council passed local law for, which requires the Casa to submit an annual report on August 30th starting in 2024 regarding the description of the steps taken to administer the Public Service Corp program in late September.
0:26:28
The council's compliance division received a notice from DECAS stating that the Naga report was taking longer than anticipated to complete, but that the report was forthcoming.
0:26:38
Can you please share the expected timeline for the submission of this report?
Katrina Porter
0:26:44
Thank you for that question, Chair.
0:26:46
So I am happy to announce that we are near completion with compiling the data for the report, and we expect to have it to the city council by the end of this month.
Carmen De La Rosa
0:26:57
By the end of November?
0:26:58
Yes.
0:26:58
End of November.
0:26:59
Great.
0:26:59
Thank you.
0:27:00
How many PSC interns were recruited in 2024?