Plans and timeline for Phase 2 of NG911 implementation
0:34:12
·
70 sec
Council Member Jennifer Gutiérrez inquires about the plans and timeline for Phase 2 of NG911 implementation. Robert Barbera explains the current status and approach to Phase 2 planning.
- Phase 2 currently does not have a definitive completion date
- It remains open-ended based on the evaluation of potential enhancements to NG911
- The schedule for testing and implementing Phase 2 enhancements will be built after the findings from the evaluation
- OTI intends to enhance multimedia support as part of the broader system improvements in Phase 2
Jennifer Gutiérrez
0:34:12
And just for my clarity, do you does the agency intend to keep phase 2 open ended?
0:34:20
You know, is there a deadline that you all are imposing on yourselves for a completion of phase 2, knowing kind of what you've shared today about what the intent is for phase 2?
Robert Barbera
0:34:30
As of today, it's not it's not, it's not it doesn't have a definitive date wrapped around it.
0:34:36
It's open ended, based upon our evaluation of enhancements that could be made within NG 911.
0:34:44
Mhmm.
0:34:45
And depending, on our findings, we would have to then build a schedule around how we would test and implement that.
Jennifer Gutiérrez
0:34:58
Okay.
0:34:59
And for phase 1, you're anticipating the completion of infrastructure services to be completed by the end of by by July 2025?
Robert Barbera
0:35:12
Correct.
Jennifer Gutiérrez
0:35:17
Okay.
0:35:17
I'm gonna, pause and pass it to my colleague, council member Batcher, who has questions.