Timeline for completion of NG911 implementation phases

0:33:36

·

33 sec

Council Member Jennifer GutiƩrrez inquires about the timeline for completing NG911 implementation phases, particularly focusing on the completion of the first phase. Robert Barbera provides information on the current projected completion date.

  • The 2022 report initially promised completion by 2024
  • The 2023 report updated the completion date to 2025
  • Barbera confirms that they are currently on schedule with the projected 2025 completion date for the first phase
  • The completion of infrastructure and services is anticipated by July 2025
Jennifer GutiƩrrez
0:33:36
I know that in the, the annual reports that have been released, they've been they've been pretty similar year to year.
0:33:45
We've noticed that, obviously, the the deadline, has been pushed out.
0:33:51
The 2022 report promised completion by 2024, and now the 2023 report promises completion in 2025.
0:34:00
Do you all anticipate pushing that deadline back any further for the completion of the first phase?
Robert Barbera
0:34:05
No.
0:34:05
At this time, we are on schedule with that projected date.
Nicole Plumbers
0:34:09
Okay.
Citymeetings.nyc pigeon logo

Is citymeetings.nyc useful to you?

I'm thrilled!

Please help me out by answering just one question.

What do you do?

Thank you!

Want to stay up to date? Sign up for the newsletter.