Superstorm Sandy funding and project completion timeline
0:59:39
ยท
56 sec
Council Member Mealy inquires about the remaining Superstorm Sandy funding and project completion timeline. Dylan Baker-Rice from NYCHA provides details on the progress and remaining projects.
- $3.3 billion received in total for Superstorm Sandy recovery
- 8 projects left to complete
- Most construction to be completed by next year, with one project extending to 2026
Darlene Mealy
0:59:39
Yes.
0:59:39
Thank you, chair.
0:59:40
I was just, wondering, you say all the repairs that you have done, that's about 27,000,000.
0:59:52
How much longer or how much more money you have from Superstorm Sandy left?
Dylan Baker-Rice
1:00:00
How much money is left?
1:00:02
Mhmm.
1:00:03
We've Could
Darlene Mealy
1:00:04
you file, finish these projects?
Dylan Baker-Rice
1:00:07
Yeah.
1:00:08
We have, 8 projects left to complete.
1:00:11
8?
1:00:12
Yeah.
1:00:13
From Superstorm Sandy, from the original funding.
1:00:16
We received 3,300,000,000 and we've committed, the majority of that funding.
1:00:24
So we're working with vendors.
1:00:26
And most of the construction will close out, by next year, with, one project projected to go into 'twenty 6.