Council Member Crystal Hudson inquires about the reasons for contract registration delays. Deputy Chancellor Simone Hawkins explains various factors that can cause these delays in the registration process.

  • Contract registration involves multiple divisions within the agency and external entities like the controller's office.
  • Delays can be caused by issues found during background checks on providers or vendors.
  • The process requires providers to submit specific information, including a contract budget, which can take time to negotiate and finalize.
Crystal Hudson
1:01:19
Okay.
1:01:19
And then what would cause a contract to not be registered?
Simone Hawkins
1:01:23
A host of things.
1:01:25
And so that is a process that's done internally across several divisions within the agency and also externally.
1:01:30
We have the support of the controller's office who also assists in that process.
1:01:34
And so sometimes it can be a background check that we find on the provider or vendor that can cause some delays.
1:01:41
We also look to the provider to provide us with some information like a budget.
1:01:46
It's different from their operating budget, it's their contract budget that needs to go with the registration packet.
1:01:51
And so in some instances that can take a little bit of time as we negotiate inputs that can cause delays with contract registration.
Citymeetings.nyc pigeon logo

Is citymeetings.nyc useful to you?

I'm thrilled!

Please help me out by answering just one question.

What do you do?

Thank you!

Want to stay up to date? Sign up for the newsletter.