Linda Tigani discusses the estimated launch costs for CORE, focusing on the development of a new database system.

  • CORE is working with OTI and OMB to build a core database system
  • The current estimated cost for the database system is approximately $208,000
  • This estimate may change as the components of the system are finalized
  • The database system is considered a launch cost as it's a new requirement for CORE
  • The system is necessary for handling data from city agencies and open data sources