Update on Rodman's Neck capital project and budget
2:09:53
ยท
52 sec
Council Member Marmorato inquires about the progress of the Rodman's Neck project in her district and seeks clarification on a budget reduction mentioned in the plan.
- The capital plan includes $258 million for a new firing range at Rodman's Neck
- The anticipated construction completion date is summer 2029
- A $38 million reduction in the plan is explained as a result of schedule changes, not actual cuts
Kristy Marmorato
2:09:53
So with capital plans, we have a big project in Rodman's Neck, and that's in my district.
2:10:01
I just wanted to know where we are with that.
Kristine Ryan
2:10:07
So Rodman's Neck, there's $258,000,000 in the capital plan for the new firing range at Robins Neck, and the anticipated construction completion date is the summer of twenty twenty nine.
Kristy Marmorato
2:10:19
Okay.
2:10:20
And then in the budget over here, it says something about where is it?
2:10:26
The plan includes a reduction of $38,000,000 Why is that?
Kristine Ryan
2:10:30
The capital plan overall?
2:10:32
It's essentially tied to just schedules changing and so depending on how the capital plan is reported, sometimes it includes 2025, sometimes it drops off.
2:10:41
So as schedules think, we shift money from year to year.
2:10:43
We're cutting anything.
Kristy Marmorato
2:10:45
Okay.