Barriers to project completion beyond funding

6:02:16

ยท

40 sec

Council Member Rita Joseph inquires about barriers that SCA faces in project completion beyond funding issues. SCA representatives discuss challenges related to new laws and regulations that impact their projects.

  • New laws and regulations constantly emerge, affecting project timelines
  • Recent example: new stormwater requirements from DEP impacting design schedules
  • SCA is working with DEP to better understand and adapt to these new requirements
Rita Joseph
6:02:16
What are some of the barriers do you face in the process which delays project completion other than funding?
6:02:24
What are some of the barriers you face?
Cora Liu
6:02:29
There are always new laws coming by.
6:02:32
There are all new regulations that we have to comply with.
6:02:36
Very recently, there is a sweep it's a storm water requirement that's coming from DEP, which we have experienced some impact on our design schedule.
6:02:48
We're working with DEP to try to understand the requirement a little better, but it is those are some examples of major hurdles we face.
Citymeetings.nyc pigeon logo

Is citymeetings.nyc useful to you?

I'm thrilled!

Please help me out by answering just one question.

What do you do?

Thank you!

Want to stay up to date? Sign up for the newsletter.