Timeline for SCA project completion after OMB approval

5:51:43

ยท

58 sec

Council Member Rita Joseph presses for specific timeframes for project completion after OMB approval. SCA officials provide estimates for different stages of the process.

  • Scope and design typically takes up to a year
  • Bid and award process takes about three months
  • Construction duration varies depending on the project, ranging from one to two years
Rita Joseph
5:51:43
So that's like how long?
5:51:44
You still didn't give me
Cora Liu
5:51:45
the Sorry.
5:51:46
From
Rita Joseph
5:51:49
From the time you get the approval from OMB and then moving forward, how long does that take?
Cora Liu
5:51:52
The scope and design typically takes up to a year and then bid award is three months.
5:51:58
Construction duration really depends on the scope and the type of the projects.
Nina Kubota
5:52:04
It could range a year or two depending on the scope of the work itself, but typically in that range.
5:52:11
I also just did want to, before I pass it to Kevin, to talk about the DSF managed projects, and this is actually one of them, PS2 I think MS2?
Rita Joseph
5:52:24
You mean MS2?
Nina Kubota
5:52:25
MS2, sorry.
5:52:26
The Computer lab.
5:52:31
Computer lab actually was previously managed by Division of School Facilities, but we actually recently took it back and it will be completed by September of this year.
Citymeetings.nyc pigeon logo

Is citymeetings.nyc useful to you?

I'm thrilled!

Please help me out by answering just one question.

What do you do?

Thank you!

Want to stay up to date? Sign up for the newsletter.