Council Member Rita Joseph presses for specific timeframes for project completion after OMB approval. SCA officials provide estimates for different stages of the process.
- Scope and design typically takes up to a year
- Bid and award process takes about three months
- Construction duration varies depending on the project, ranging from one to two years
Rita Joseph
5:51:43
So that's like how long?
5:51:44
You still didn't give me
Cora Liu
5:51:45
the Sorry.
5:51:46
From
Rita Joseph
5:51:49
From the time you get the approval from OMB and then moving forward, how long does that take?
Cora Liu
5:51:52
The scope and design typically takes up to a year and then bid award is three months.
5:51:58
Construction duration really depends on the scope and the type of the projects.
Nina Kubota
5:52:04
It could range a year or two depending on the scope of the work itself, but typically in that range.
5:52:11
I also just did want to, before I pass it to Kevin, to talk about the DSF managed projects, and this is actually one of them, PS2 I think MS2?
Rita Joseph
5:52:24
You mean MS2?
Nina Kubota
5:52:25
MS2, sorry.
5:52:26
The Computer lab.
5:52:31
Computer lab actually was previously managed by Division of School Facilities, but we actually recently took it back and it will be completed by September of this year.