Capital projects update: Woodside facility reconstruction

4:13:57

·

66 sec

Commissioner Do provides an update on TLC's major capital project, the reconstruction of the safety and emissions inspection facility in Woodside, Queens.

  • The project has a budget of $180 million and is currently in its first phase.
  • It is expected to be substantially completed by the end of 2028.
  • The project is currently at 18.2% completion.
  • Once completed, the new facility will increase inspection capacity by 200 cars per day.
  • The project scope was expanded to include 70 new electric vehicle chargers, including 30 level three fast chargers.
  • The city will seek partial reimbursement for charger installation from grants such as Con Edison's Power Ready program.
  • The project also includes a new administrative building and parking garage for TLC employees.