Council Member Julie Won questions DOT on daylighting implementation costs

1:40:03

·

102 sec

Video Player is loading.
Current Time 0:00
Duration 0:00
Loaded: 0%
Stream Type LIVE
Remaining Time 0:00
Â
1x
    • Chapters
    • descriptions off, selected
    • captions off, selected

      Council Member Julie Won questions DOT representatives about the costs and staffing requirements for implementing hardened daylighting across New York City. She challenges the DOT's cost estimates and asks for clarification on various aspects of the implementation process.

      • Won questions the need for additional $2 million in staffing costs on top of the estimated $10,000 per intersection.
      • She inquires about potential cost-sharing with DEP for rain garden implementations.
      • Won asks about the timeline for implementing 1,000 daylit locations per year and ways to speed up the process.