      Keith Grossman provides a comprehensive explanation of NYCHA's process for testing and maintaining boiler systems in response to Council Member Chris Banks' request.

      • Boilers are opened and checked on both the hot water and heat sides
      • All components and mechanical pieces are inspected, repaired, or replaced as needed
      • A hydro test is performed to check for leaks
      • Supervisory inspections are conducted to ensure satisfactory work
      • The process continues until the asset is 100% ready for service