    Council Member Brooks-Powers inquires about the status and timeline of the Brookville Park bathroom project. DDC officials provide updates on the project's progress and explain the design-build timeline.

    • The project has been awarded to an MWBE contractor, Armond
    • Notice to proceed will be issued this summer
    • The contractor has an 18-month timeline to complete six restrooms, including Brookville Park
    • DDC considers the 18-month timeline to be aggressive for design and construction
    • Council Member expresses concerns about the length of time since funding was secured