Green infrastructure implementation in MS4 areas

2:12:08

·

112 sec

Deputy Commissioner Licata discusses the strategic approach to implementing green infrastructure in MS4 areas, focusing on projects that offer multiple benefits such as improving water quality and reducing flooding.

  • Collaboration with the Trust for Public Land and Parks Department on public on-site projects
  • Cloudburst projects in St. Albans right of way and Rufus King Park
  • Upcoming project in Archie Spigner Park
  • Montbullier Cloudburst Hub design planned to start in FY 2029, draining to Thurston Basin
James F. Gennaro
2:12:08
Here's the question.
2:12:09
What are the most common types of green infrastructure that DEP and other partnering agencies have been able to install in MS 4 areas?
2:12:20
We kinda touched on this a little bit, but just to kinda clarify it.
Angela Licata
2:12:25
Yeah, we have.
2:12:26
It's very varied.
2:12:29
As we've been discussing, we've been looking to be very strategic in the MS4 area by identifying locations where we can get multiple benefits.
2:12:39
We can improve the water quality by removing the pollutant loads, and we can also address and reduce flooding.
2:12:48
So we have a number of public on-site projects that we're doing with the Trust for Public Land and the Parks Department.
2:12:56
We have two really excellent examples of our Cloudburst project.
2:13:01
One is going to be in St.
2:13:02
Albans right of way.
2:13:04
Another is at the Rufus King Park.
James F. Gennaro
2:13:07
Oh, that used to be in my district.
Angela Licata
2:13:10
There we go.
James F. Gennaro
2:13:11
I just lost it.
Angela Licata
2:13:12
Yeah.
2:13:13
St.
2:13:13
Albans right of way is in design, and Rufus King Park, we have bid the procurement.
James F. Gennaro
2:13:20
What are you gonna do in Rufus King?
Angela Licata
2:13:23
So that's gonna be cloudburst management, working with some opportunity to direct water from the streets and to utilize the low lying areas and wet areas of the park.
James F. Gennaro
2:13:36
Okay.
2:13:38
Thank you.
Angela Licata
2:13:40
We also have another one in Archie Spigner Park, which is also looking to be bid soon.
2:13:48
I'm gonna put it that way.
2:13:49
And we have the Montbullier Cloudburst Hub.
2:13:52
The design will start in FY twenty nine.
2:13:56
That's very close and drains to Thurston Basin.
2:13:59
Thank
Citymeetings.nyc pigeon logo

Is citymeetings.nyc useful to you?

I'm thrilled!

Please help me out by answering just one question.

What do you do?

Thank you!

Want to stay up to date? Sign up for the newsletter.