DOT officials explain capital project timeline and procurement process

2:19:19

·

87 sec

DOT officials explain the standard timeline and process for capital projects in response to Council Member Ossé's concerns about efficiency. The discussion covers the various stages involved in project implementation and the reasons for the lengthy timeline.

  • Standard timeline for capital projects is about six years from concept to completion
  • Process involves multiple stages: idea conception, design, presentation, bidding, and construction
  • Procurement process and design phase contribute significantly to the timeline
  • DOT often works with the Department of Design and Construction (DDC) on these projects
Chi A. Ossé
2:19:19
This site should certainly start first, I think.
2:19:22
What is the agency doing around expediting this process?
2:19:26
I mean, six years is the fact that that is a norm for a project.
2:19:30
What is the Commissioner, what work have you been doing over the past four years to condense that that period of time for when a project comes into completion?
2:19:38
Seems very inefficient.
Ydanis Rodriguez
2:19:40
Yeah.
2:19:40
It it it's about all the procurement process that go through a project.
Chi A. Ossé
2:19:46
No.
2:19:46
I understand that.
2:19:47
What are you doing to Listen.
Chris Banks
2:19:48
Are you
Ydanis Rodriguez
2:19:48
gonna be seeing I gonna be seeing now probably I will I started and and again, it should be your expectation that Mhmm.
2:19:59
We should change what has not worked in the past.
2:20:02
But I can tell you when I was elected in my first budget, I put $5,500,000.
Chi A. Ossé
2:20:08
Sure.
2:20:09
Sure.
2:20:09
So what do you so who's If you don't mind.
2:20:12
Who's responsible for for the delay in that procurement?
2:20:14
It's not Nothing on your end.
Ydanis Rodriguez
2:20:16
No.
2:20:17
Listen.
2:20:17
That's another part of the story.
2:20:19
But let me give you with this.
2:20:20
We can get back to you with more details.
2:20:22
Sure.
2:20:23
Timing is the right one that we have in front of us.
2:20:26
Capital project is take a lot from the moment as Paul described.
2:20:30
Everything that you take it from the idea to the concept, to the designing, to present it, to the bid.
2:20:37
So again, we heard you loud and clear.
2:20:39
I'm more than happy to see I tried to figure out a way of how we can move quickly.
2:20:43
But the timing is standard timing for any company.
Citymeetings.nyc pigeon logo

Is citymeetings.nyc useful to you?

I'm thrilled!

Please help me out by answering just one question.

What do you do?

Thank you!

Want to stay up to date? Sign up for the newsletter.