Funding for major street reconstruction projects
0:20:37
·
68 sec
Commissioner Rodriguez details funding allocations for several major street reconstruction projects across the city.
- $101 million is allocated for street reconstruction projects that build out critical safety improvements in permanent concrete materials
- Key projects include:
- $79.6 million for phase four of the Queens Boulevard redesign (Yellowstone Boulevard to Union Turnpike)
- $13.3 million for the Northern Boulevard-Douglaston Connector project
- $4.7 million for the Van Sinderen Avenue streetscape project in the Broadway Junction area
- $3.7 million for the Park Avenue pedestrian safety improvement project near the BQE
Ydanis Rodriguez
0:20:37
And this budget include 101,000,000 for a street reconstruction project that build our out critical safety improvement in permanent concrete materials.
0:20:49
This include 79,600,000.0 for the four phase of our Queens Boulevard redesign that will extend the improvement from Yellowstone Boulevard to Union Turnpike.
0:21:04
13 Point 3 Million for our Northern Boulevard, Douglas Stone Connector project to build out the cyclist transition or Northern Boulevard at the Cross Island Parkway.
0:21:17
4 Point 7 Million for the Van Sinderen Avenue, a street escape project that will expand public space and improve pedestrian safety in the Broadway Junction area.
0:21:31
And 3,700,000.0 for the Park Avenue pedestrian safety improvement project that will slow traffic and create a new public space under the BQE.