Revision of project completion time metrics

6:03:00

ยท

32 sec

Council Member Rita Joseph inquires about the revision of the project completion time metric from 15 days to 30 days after the scheduled date. SCA representatives explain the reasoning behind this change.

  • The metric was revised to align with other city agencies' standards
  • SCA was unsure why it was initially set at 15 days
  • The change to 30 days brings SCA in line with other capital agencies' metrics
Rita Joseph
6:03:00
Thank you.
6:03:00
In the fiscal twenty twenty five PMMR, the metric regarding the percentage of projects constructed on time or early was revised from fifteen days after the scheduled date to 30.
6:03:11
Why was the metric revised to give SCA more time to complete a project to be considered on time?
Nina Kubota
6:03:17
Actually we just aligned that with other city agencies use that same metric.
6:03:23
We were not sure why it was fifteen days initially, so we just all all the capital agencies use that thirty days, so we just aligned it with So
Rita Joseph
6:03:31
everyone could be on the same page in the line.
Citymeetings.nyc pigeon logo

Is citymeetings.nyc useful to you?

I'm thrilled!

Please help me out by answering just one question.

What do you do?

Thank you!

Want to stay up to date? Sign up for the newsletter.