The Brownsville NCP project offers a range of affordability levels and unit sizes across the three buildings, with adjustments made in response to community feedback and the City of Yes updates.

  • Approximately 70% of units available to households earning up to 60% of Area Median Income (AMI)
  • Increased percentage of units in the 40% AMI tier in response to community feedback
  • Highest tier set at 70% AMI, as 80% AMI was considered too high by the community
  • Mix of studios, one-bedroom, two-bedroom, and three-bedroom units, with 39 units suitable for families
  • Eight units set aside for formerly homeless households
  • Addition of 14 units due to City of Yes updates, allowing for deeper affordability
Amhara Hernandez
0:13:40
Next slide, please.
0:13:44
So, I described before the project is under the neighborhood construction program and this chart is illustrating the project total and unit mix for all three buildings.
0:13:56
The project was able to add 14 units and one super across the three buildings after the city of Yes updates.
0:14:02
And in response to the c b 16 recommendation for deeper affordability, the project prioritized increasing the percentage of units in the 40% AMI tier.
0:14:12
Approximately 70% of units in the project are available to households earning up to 60% of area median income.
0:14:18
Additionally, based on prior c b 16 and community feedback, we are also keeping the highest tier at 70% AMI since we heard that 80% AMI tier is too high as well.
0:14:32
The three buildings also provide a mix of studios, one bedrooms, and two and three bedrooms as well with 39 being large enough for family size households.
0:14:40
We also have eight units set aside for formerly homeless households in a variety of unit sizes.
0:14:45
You can go on to the next slide.
0:14:48
This slide just provides a little bit of a unit a project summary.
0:14:52
So after the City of Yes, we were able to add 14 additional units.
0:14:56
So the project is able to have up to 74 units with an additional supers unit across all three.
0:15:01
It is a small scattered site project that is more feasible due to it being together.
0:15:06
And Fifth Avenue Committee has been working for many years to, you know, get this project on its feet and also get to this milestone today.
0:15:13
So we're very excited.
0:15:14
The original project that was proposed was 60 units.
0:15:17
So having these additional units was enabled us to deepen affordability and add more units to the 40% AMI tier.
0:15:25
We also have over 2,000 square feet of community facility or retail space in development Site 1 Mother Gas And Boulevard that we have been actively seeking input on for a tenant.
0:15:36
And we will pass it back to you for comments and questions.
0:15:39
Thank you.
Citymeetings.nyc pigeon logo

Is citymeetings.nyc useful to you?

I'm thrilled!

Please help me out by answering just one question.

What do you do?

Thank you!

Want to stay up to date? Sign up for the newsletter.